  • jamal bahri commented,

    let be K=[k1,k2,k3..km] a set of commodities of demand D=[d1..dm]  to be migrated from thier old path Pold=[Po1,Po2..Pom] to thier final Path Pf=[Pf1,Pf2..Pfm] y[k,t]  binary denote that flow k is ...

  • jamal bahri created a post,

    modeling flow management problem

    Answered

    thanks to help me encode variable dependency  for flow management problem: i' have constraints on capacity on each arcs at each step some flow should be migrated ; but i need to express non violati...